Soil improvement was carried out with pre-loading for 3 tanks on an area of about 13 000m2 in Ploce Port according to our foundation calculations (soft soil up to 40m). Measured settlement values during the pre-loading process compared to the...

Reconstruction of the land part of ACI port Rovinj is finnished. Our design rationalized the foundation type and avoided underwater construction works....

2 Tanks (2 x 30 000m3) were constructed in Ploce Port according to our foundation calculations (soft soil up to 40m). Measured settlement values during hydrotest compared to the calculated ones in the numerical model were around 10-20%...